What is a project baseline?

A baseline is a snapshot of the approved plan. Without it, you can see that dates moved but not by how much.

Try it freeSee pricingFree for up to 3 plans of 50 lines.
Baseline and variance
TASKBASELINE (grey) vs CURRENTWireframeson planVisual design+2 dFrontend+4 dTesting+5 d

What goes into it

For a schedule baseline: each task's start, finish and duration at the moment the plan was agreed. Scope and cost baselines work the same way for their subjects.

Schedule variance

Variance is current finish minus baseline finish, in working days. A positive number means late. Look at the critical tasks first: variance there moves the end date.

When to re-baseline

  • After a formally approved change in scope or deadline.
  • Not just because the project slipped. Keeping the old baseline is how you learn.

In GenuinePlan you save a baseline in one click and see ghost bars on the chart.

Frequently asked questions

Is a baseline the same as a forecast?

No. The baseline is what was planned. The forecast is the current expectation.