How to write a project status report

A status report is read in two minutes by people with other things to do. Make those two minutes count.

Try it freeSee pricingFree for up to 3 plans of 50 lines.

The outline

  1. Overall health. On track, at risk or behind, in one word, with the reason.
  2. Progress. Percent complete and what was finished since the last report.
  3. Schedule. Planned versus forecast finish. Use a baseline so the gap is a number.
  4. Risks and issues. What could or did go wrong, and what you are doing about it.
  5. Next period. What will be done, and who is on it.
  6. Asks. Decisions or help you need from the reader.

Tips

  • Lead with the answer; details come after.
  • Use numbers from the plan instead of adjectives.
  • Keep the format the same every time so changes stand out.

GenuinePlan fills in health, progress, overdue tasks and variance from the plan: status report PDF.

Frequently asked questions

How often should I send a status report?

Match the pace of the project: weekly is common, fortnightly for slower work.